请帮忙给出正确答案和分析,谢谢!
第1题
Total Project Risk:
A should not be calculated for small projects
B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D A and B
E A and C
第2题
The total amount of risk that is calculated for a project is found by:
A.Multiplying the sum of each the risks times the amount at stake
B.Calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events
C.Cannot be calculated since all risks are not known
D.The amount of project reserves available
第3题
122 Total Project Risk:
A. should not be calculated for small projects
B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D. A and B
E. A and C
第4题
4 Total Project Risk:
A. should not be calculated for small projects
B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D. A and B
E. A and C
第5题
52 Project Risk _____ .
A. should not be calculated for small projects.
B. is the probability of each risk event minus the sum of the consequences of potential risk events.
C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives. D. cannot be quantified for first time projects.
E. B or D
第6题
170 Project Risk _____ .
A. should not be calculated for small projects.
B. is the probability of each risk event minus the sum of the consequences of potential risk events.
C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.
D. cannot be quantified for first time projects.
E. B or D
第7题
The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.
第8题
194 The schedule risk is the _____ .
A. the accumulated "expected' durations which maintain project completion.
B. Critical Path adjusted by "high-risk" activity float.
C. highest risk path that maintains quality.
D. Critical Path when calculated with "most likely" duration.
E. highest risk path that contributes the most risk toward the project completion
第9题
112 The schedule risk is the _____ .
A. the accumulated "expected' durations which maintain project completion.
B. Critical Path adjusted by "high-risk" activity float.
C. highest risk path that maintains quality.
D. Critical Path when calculated with "most likely" duration.
E. highest risk path that contributes the most risk toward the project completion
第10题
Total project risk can be defined as:
A the sum of the probabilities of project risks events times the sum of consequences of those risks
B the sum of the products of each project risk event times its consequences
C the sum of the consequences of all project risk events
D the sum of the probabilities of all project risk events
E 1 - the sum of the probabilities of all project risk events.
为了保护您的账号安全,请在“上学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!