第1题
Project Risk _____ .
A should not be calculated for small projects.
B is the probability of each risk event minus the sum of the consequences of potential risk events.
C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.
D cannot be quantified for first time projects.
E B or D
第2题
The total amount of risk that is calculated for a project is found by:
A.Multiplying the sum of each the risks times the amount at stake
B.Calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events
C.Cannot be calculated since all risks are not known
D.The amount of project reserves available
第3题
122 Total Project Risk:
A. should not be calculated for small projects
B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D. A and B
E. A and C
第4题
4 Total Project Risk:
A. should not be calculated for small projects
B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D. A and B
E. A and C
第5题
Total project risk can be defined as:
A the sum of the probabilities of project risks events times the sum of consequences of those risks
B the sum of the products of each project risk event times its consequences
C the sum of the consequences of all project risk events
D the sum of the probabilities of all project risk events
E 1 - the sum of the probabilities of all project risk events.
第6题
A.Nothing, the risk design is complete
B.The risk probabilities need to be summed to determine the total project risk
C.The risk events must be labeled as internal or external risk events
D.The risk events do not address the technology used by the Boston project
E.The impact of the risk on the project’s objectives has not been assessed and assigned
第7题
52 Project Risk _____ .
A. should not be calculated for small projects.
B. is the probability of each risk event minus the sum of the consequences of potential risk events.
C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives. D. cannot be quantified for first time projects.
E. B or D
第8题
170 Project Risk _____ .
A. should not be calculated for small projects.
B. is the probability of each risk event minus the sum of the consequences of potential risk events.
C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.
D. cannot be quantified for first time projects.
E. B or D
第9题
15 Total project risk can be defined as:
A. the sum of the probabilities of project risks events times the sum of consequences of those risks
B. the sum of the products of each project risk event times its consequences
C. the sum of the consequences of all project risk events
D. the sum of the probabilities of all project risk events
E. 1 - the sum of the probabilities of all project risk events
第10题
97 Total project risk can be defined as:
A. the sum of the probabilities of project risks events times the sum of consequences of those risks
B. the sum of the products of each project risk event times its consequences
C. the sum of the consequences of all project risk events
D. the sum of the probabilities of all project risk events
E. 1 - the sum of the probabilities of all project risk events