请帮忙给出正确答案和分析,谢谢!
第1题
112 The schedule risk is the _____ .
A. the accumulated "expected' durations which maintain project completion.
B. Critical Path adjusted by "high-risk" activity float.
C. highest risk path that maintains quality.
D. Critical Path when calculated with "most likely" duration.
E. highest risk path that contributes the most risk toward the project completion
第2题
194 The schedule risk is the _____ .
A. the accumulated "expected' durations which maintain project completion.
B. Critical Path adjusted by "high-risk" activity float.
C. highest risk path that maintains quality.
D. Critical Path when calculated with "most likely" duration.
E. highest risk path that contributes the most risk toward the project completion
第3题
A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
第4题
Which of the following does not contribute to increased Schedule Risk?
A labor shortage
B contractor claims
C lack of access
D sponsor scope changes
E all may increase schedule risk
第5题
7 Which of the following does not contribute to increased Schedule Risk?
A. labor shortage
B. contractor claims
C. lack of access
D. sponsor scope changes
E. all may increase schedule risk
第6题
125 Which of the following does not contribute to increased Schedule Risk?
A. labor shortage
B. contractor claims
C. lack of access
D. sponsor scope changes
E. all may increase schedule risk
第7题
Risk event probability is defined as:
A the total number of possible events divided into the expectations or frequency of the risk event
B the number of times the risk event may occur
C the fraction of the total project tasks which may be affected by the risk event
D the total number of possible events divided into the consequences of the risk event.
E A and B
第8题
Project Risk Management is based on which of the following premises:
A the future is unknown.
B unknowns can result in risks or opportunities.
C we cannot control risk events.
D project risk impact can be measured and controlled
E All of the above.
第9题
Risk exposure refers to _____ .
A the amount at stake.
B what might happen.
C the likelihood of something
D who is going to be held accountable
E All of the above.
第10题
Total project risk can be defined as:
A the sum of the probabilities of project risks events times the sum of consequences of those risks
B the sum of the products of each project risk event times its consequences
C the sum of the consequences of all project risk events
D the sum of the probabilities of all project risk events
E 1 - the sum of the probabilities of all project risk events.
为了保护您的账号安全,请在“上学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!