● The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A Increases.
B Is not affected by
C Does not require
D Is heavily dependent upon
E Is the only means of determining
第2题
101 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A. Increases.
B. Is not affected by
C. Does not require
D. Is heavily dependent upon
E. Is the only means of determining
第3题
183 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A. Increases.
B. Is not affected by
C. Does not require
D. Is heavily dependent upon
E. Is the only means of determining
第4题
The first step in building a PERT/CPM network is to:
A.Create a flow chart
B.Determine the critical path
C.Show task relationships
D.Create a work breakdown structure
E.None of the above.
第5题
● The first step in building a PERT/CPM network is to:
A Create a flow chart
B Determine the critical path
C Show task relationships
D Create a work breakdown structure
E None of the above.
第6题
190 The first step in building a PERT/CPM network is to:
A. Create a flow chart
B. Determine the critical path
C. Show task relationships
D. Create a work breakdown structure
E. None of the above
第7题
72 The first step in building a PERT/CPM network is to:
A. Create a flow chart
B. Determine the critical path
C. Show task relationships
D. Create a work breakdown structure
E. None of the above
第8题
47 The major difference between PERT and CPM networks is:
A. PERT requires three time estimates whereas CPM requires one time estimate.
B. PERT is used for construction projects whereas CPM is used for R & D.
C. PERT addresses only time whereas CPM also includes cost and resource availability.
D. PERT requires computer solutions whereas CPM is a manual technique.
E. PERT is measured in days whereas CPM uses weeks or months
第9题
A.CPM的工作逻辑关系肯定,PERT的工作逻辑关系不确定
B.CPM使用最大可能工作时间估计,PERT使用加权平均时间估计
C.CPM的工作必须进行,PERT的某些工作可以不进行
D.CPM不允许存在回路,PERT中可以存在回路
为了保护您的账号安全,请在“上学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!