第1题
The first step in building a PERT/CPM network is to:
A.Create a flow chart
B.Determine the critical path
C.Show task relationships
D.Create a work breakdown structure
E.None of the above.
第2题
72 The first step in building a PERT/CPM network is to:
A. Create a flow chart
B. Determine the critical path
C. Show task relationships
D. Create a work breakdown structure
E. None of the above
第3题
190 The first step in building a PERT/CPM network is to:
A. Create a flow chart
B. Determine the critical path
C. Show task relationships
D. Create a work breakdown structure
E. None of the above
第4题
● The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A Increases.
B Is not affected by
C Does not require
D Is heavily dependent upon
E Is the only means of determining
第5题
101 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A. Increases.
B. Is not affected by
C. Does not require
D. Is heavily dependent upon
E. Is the only means of determining
第6题
183 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A. Increases.
B. Is not affected by
C. Does not require
D. Is heavily dependent upon
E. Is the only means of determining
第7题
A.Increases.
B.Is not affected by
C.Does not require
D.Is heavily dependent upon
E.Is the only means of determining
第8题
47 The major difference between PERT and CPM networks is:
A. PERT requires three time estimates whereas CPM requires one time estimate.
B. PERT is used for construction projects whereas CPM is used for R & D.
C. PERT addresses only time whereas CPM also includes cost and resource availability.
D. PERT requires computer solutions whereas CPM is a manual technique.
E. PERT is measured in days whereas CPM uses weeks or months
第9题
129 The major difference between PERT and CPM networks is:
A. PERT requires three time estimates whereas CPM requires one time estimate.
B. PERT is used for construction projects whereas CPM is used for R & D.
C. PERT addresses only time whereas CPM also includes cost and resource availability.
D. PERT requires computer solutions whereas CPM is a manual technique.
E. PERT is measured in days whereas CPM uses weeks or months