Management by objectives of a works only if:
A.it is supported by management.
B.the rules are written down.
C.the project does not impact the objectives.
D.the project includes the objectives in the charter.
第1题
Which of the following statements is true?
A.Properly operated projects often go through progressive elaboration, not remaining fixed even though the scope has been defined and agreed.
B.The project to create the Shanxia (Three-Gorges ) Dam can't be considered temporary because of the operations such as power generation , transformation of electric power , transportation , etc . are following after the Dam has been completed.
C.Projects can go on indefinitely when there is support and maintenance involved.
D.Projects are not unique because there is always some aspect that has been done before.
第2题
A.Feasibility
B.Executing
C.Planning
D.Closing
第3题
the followings is most true?
A.The project life cycle typically changes and evolves with the project.
B.The project management life cycle is unique to every project.
C.The project life cycle is can be referred to as the Project Management Life Cycle.
D.The product life cycle typically involves more than one project life cycle.
第4题
质量保证除为项目提供支持外,还为什么创造了条件?
A.计划一实施一检查—行动
B.持续的过程改进
C.项目管理成熟度
D.工作绩效信息
第5题
,此人专攻适用于团队的工作环境改造学。她决定观察你和团队成员的工作方法,以确定新系统的要求。这种方法也称做()。
A.监视
B.教练
C.工作跟踪
D.用户实验法
第8题
交了变更请求,希望扩大其工作范围。你根据对此请求的评审,决定对合同进行修订。以上属于哪项活动?
A.管理采购
B.实施采购
C.形成合同
D.解决争议
第9题
是建议书经理。评估标准中规定的一个要求时,项目经理必须是PMP。你认为卡特里娜是担任这份工作的合适人选,但是她要在提交建议书的截止日期的两个星期之后才参加考试。卡特里娜拥有项目管理的硕士学位以及所需的经验。她已经为参加考试准备了几个星期,她自信能通过考试。而且她还有所需的技术专长。理查德是公司里的另一位PMP,他已完全投入另一个项目。在准备建议书时,你应该:
A.将理查德作为项目经理的人选并提交其简历,因为他是PMP;合同裁定之后,在客户同意的基础上把他换成卡特里娜
B.提交卡特里娜的简历并说她是PMP,因为你知道她能通过考试并得到资格证书
C.在你的建议书中指明卡特里娜在PMP资格证书方面的现状,并将她作为项目经理的人选并提交其简历
D.在建议书中将拉斯作为项目经理的人选并提交其简历。拉斯是PMP,她申请过公司的一个职位,但还未被录用
第10题
在以下什么文件中?
A.项目章程
B.范围说明
C.衡量进度绩效与成本绩效的基准计划
D.来自于其他知识领域的独立的管理计划