A.Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).
B.Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.
C.The skill level of the added resources might not be appropriate for the activities to be performed.
D.Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)
E.All of the above.