Interfacing with the customer after project go-ahead is the responsibility of:
AProject sponsor
BProject team
CProject manager
DFunctional manager
EAll of the above are possible, based upon the size and complexity of the project
第2题
100 Interfacing with the customer after project go-ahead is the responsibility of:
A. Project sponsor
B. Project team
C. Project manager
D. Functional manager
E. All of the above are possible, based upon the size and complexity of the project
第3题
18 Interfacing with the customer after project go-ahead is the responsibility of:
A. Project sponsor
B. Project team
C. Project manager
D. Functional manager
E. All of the above are possible, based upon the size and complexity of the project
第4题
55 The core function of the project manager is
A. Systems design
B. Client interfacing
C. Quality assurance
D. integration
第5题
137 The core function of the project manager is
A. Systems design
B. Client interfacing
C. Quality assurance
D. integration
第6题
第7题
The core function of the project manager is
A . Systems design
B . Client interfacing
C . Quality assurance
D . integration
第8题
52 The core function of the PM is
A. client interfacing
B. project integration
C. quality assurance
D. personal administration
E. All of the above
第9题
134 The core function of the PM is
A. client interfacing
B. project integration
C. quality assurance
D. personal administration
E. All of the above
第10题
Including the customer in the process of project planning is:
A.Slow and counterproductive.
B.Essential in the definition and documentation of project goals.
C.Necessary, but of limited value.
D.Unnecessary because project goals are defined in the proposal stage.
E.None of the above.
为了保护您的账号安全,请在“上学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!