重要提示: 请勿将账号共享给其他人使用,违者账号将被封禁!
查看《购买须知》>>>
找答案首页 > 全部分类 > 职业资格考试
搜题
网友您好, 请在下方输入框内输入要搜索的题目:
搜题
题目内容 (请给出正确答案)
[主观题]

依据简单过滤器规则,如果股票价格相对于参考基准上升的幅度达到了预先设定的百分比,就卖出该股票

;而如果股票价格相对于参考基准下跌的幅度达到了预先设定的百分比,就买入该股票。()

A.正确

B.错误

查看答案
更多“依据简单过滤器规则,如果股票价格相对于参考基准上升的幅度达到了预先设定的百分比,就卖出该股票”相关的问题

第1题

160The project manager has, as a prime responsibility, to assure proper integration of act

160 The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work? A. Matrix

B. Classical

C. Expediter

D. Coordinator

E. Pure project

点击查看答案

第2题

The project manager has, as a prime responsibility, to assure proper integration of activi
ties. In which organizational form. does the project manager probably have the easiest time in integrating work?

A . Matrix

B . Classical

C . Expediter

D . Coordinator

E . Pure project

点击查看答案

第3题

112Of the following, who has the ultimate responsibility for meeting project quality objec

112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner

点击查看答案

第4题

194Of the following, who has the ultimate responsibility for meeting project quality objec

194 Of the following, who has the ultimate responsibility for meeting project quality objectives?

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner

点击查看答案

第5题

Of the following, who has the ultimate responsibility for meeting project quality objectiv
es?

A . Project Engineer

B . Project Manager

C . Functional Manager

D . Quality Assurance Manager

E . Project Owner

点击查看答案

第6题

The contracting function in an organization is considered to be decentralized when ()

The contracting function in an organization is considered to be decentralized when ()

A.Each project manager has control over the contracting process for his or her project

B.The project manager controls contract award

C.The contracting person appointed to the project is available and under the project manager's direct control

D.Contracting is tailored to a single project

E.All above

点击查看答案

第7题

Management tells a project manager to subcontract part of the project to a company that ma
nagement has worked with many times . Under these circumstances, the project manager should be MOST concerned about:

A.making sure the company has the qualifications to complete the project .

B.meeting management expectations of time .

C.the cost of the subcontracted work .

D.the contract terms and conditions .

点击查看答案

第8题

A project manager is assigned to a project . This type of project has never been done
before . The project manager has decided to build a basic project schedule and to detail the work of each phase as the current phase nears completion . What BEST descri

A.The controlling process of ensuring that project objectives are met by taking corrective action when necessary .

B.The process of planning change control .

C.The progressive process of rolling wave planning .

D.The core planning process of reiterating a plan in the same order from project to project .

点击查看答案

第9题

The customer on a project tells the project manager he has run out of money to pay for the
project . What should the project manager do FIRST ?

A.Shift more of the work to later in the schedule to allow time for the customer to get the funds .

B.Reduce the scope of work and enter closure .

C.Stop work .

D.Release part of the project team .

点击查看答案

第10题

A seller has withdrawn from a project midway though execution and another seller is taking
over . The project manager meets with the replacement seller and his crew . In this meeting, what should the project manager do FIRST ?

A.Introduce team members .

B.Communicate the objectives of the project .

C.Assert authority .

D.Create a communications plan .

点击查看答案
下载上学吧APP
客服
TOP
重置密码
账号:
旧密码:
新密码:
确认密码:
确认修改
购买搜题卡查看答案
购买前请仔细阅读《购买须知》
请选择支付方式
微信支付
支付宝支付
选择优惠券
优惠券
请选择
点击支付即表示你同意并接受《服务协议》《购买须知》
立即支付
搜题卡使用说明

1. 搜题次数扣减规则:

功能 扣减规则
基础费
(查看答案)
加收费
(AI功能)
文字搜题、查看答案 1/每题 0/每次
语音搜题、查看答案 1/每题 2/每次
单题拍照识别、查看答案 1/每题 2/每次
整页拍照识别、查看答案 1/每题 5/每次

备注:网站、APP、小程序均支持文字搜题、查看答案;语音搜题、单题拍照识别、整页拍照识别仅APP、小程序支持。

2. 使用语音搜索、拍照搜索等AI功能需安装APP(或打开微信小程序)。

3. 搜题卡过期将作废,不支持退款,请在有效期内使用完毕。

请使用微信扫码支付(元)
订单号:
遇到问题请联系在线客服
请不要关闭本页面,支付完成后请点击【支付完成】按钮
遇到问题请联系在线客服
恭喜您,购买搜题卡成功 系统为您生成的账号密码如下:
重要提示: 请勿将账号共享给其他人使用,违者账号将被封禁。
发送账号到微信 保存账号查看答案
怕账号密码记不住?建议关注微信公众号绑定微信,开通微信扫码登录功能
警告:系统检测到您的账号存在安全风险

为了保护您的账号安全,请在“上学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!

- 微信扫码关注上学吧 -
警告:系统检测到您的账号存在安全风险
抱歉,您的账号因涉嫌违反上学吧购买须知被冻结。您可在“上学吧”微信公众号中的“官网服务”-“账号解封申请”申请解封,或联系客服
- 微信扫码关注上学吧 -
请用微信扫码测试
选择优惠券
确认选择
谢谢您的反馈

您认为本题答案有误,我们将认真、仔细核查,如果您知道正确答案,欢迎您来纠错

上学吧找答案