第1题
The main player in project communication is the
A sponsor
B project manager
C functional manager
D functional team
E All of the above.
第2题
174 The main player in project communication is the
A. sponsor
B. project manager
C. functional manager
D. functional team
E. All of the above
第3题
92 The project charter is developed by:
A. senior management
B. the customer
C. the project manager
D. both A and C
E. None of the above
第4题
92 The highest degrees of project risk and uncertainty are associated with the following phase of the project:
A. conceptual
B. execution
C. cut-over
'D. post project evaluation
E. A and D only
第5题
92 The most common form. of organizational communication is
A. Upward to management
B. Downward to subordinates
C. Horizontal to peers
D. Horizontal to customers
E. All of the above
第6题
A.10
B.45
C.50
D.100
第7题
A.10
B.45
C.50
D.100
第8题
173 Five people are involved on a project that requires significant communication between all project participants. How many lines of communication exist on this project?
A. 5
B. 6
C. 8
D. 10
E. 9
第9题
55 Five people are involved on a project that requires significant communication between all project participants. How many lines of communication exist on this project?
A. 5
B. 6
C. 8
D. 10
E. 9
第10题
A.The communication management plan is contained in, or is a subsidiary plan of, the project management plan
B.The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project
C.The communication management plan organize and summarize the information gathered, and present the results of any analysis as compared to the performance measurement baseline
D.The communication management plan can include guidelines for project status meetings, project team meetings, e-meetings, and e-mails