Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A . 2
B . 3
C . 4
D . 5
E . 7
第2题
● Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A 2
B 3
C 4
D 5
E 7
第3题
120 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A. 2
B. 3
C. 4
D. 5
E. 7
第4题
● Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A 0
B 1
C 2
D 3
E 4
第5题
2 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A. 2
B. 3
C. 4
D. 5
E. 7
第6题
● Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.
A 2, 10
B 4, 12
C 6, 14
D 7, 15
E 9, 17
第7题
● Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.
A 11, 13
B 12, 14
C 13, 15
D 14, 16
E 15, 17
第8题
111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A. 0
B. 1
C. 2
D. 3
E. 4
第9题
193 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A. 0
B. 1
C. 2
D. 3
E. 4
第10题
117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.
A. 11, 13
B. 12, 14
C. 13, 15
D. 14, 16
E. 15, 17