请帮忙给出正确答案和分析,谢谢!
第1题
193 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A. 0
B. 1
C. 2
D. 3
E. 4
第2题
111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A. 0
B. 1
C. 2
D. 3
E. 4
第3题
Using the figure in the Special window, The Critical path is _____ weeks.
A . 21
B . 22
C . 23
D . 24
E . 25
第4题
● Using the figure in the Special window, The Critical path is _____ weeks.
A 21
B 22
C 23
D 24
E 25
第5题
● Using the figure in the Special window, The critical path is:
A A-B-G
B C-G
C C-D
D E-F
E A-B-G and C-D
第6题
Using the figure in the Special window, The critical path is:
A . A-B-G
B . C-G
C . C-D
D . E-F
E . A-B-G and C-D
第7题
● Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A 2
B 3
C 4
D 5
E 7
第8题
Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A . 2
B . 3
C . 4
D . 5
E . 7
第9题
Using the figure in the Special Window, what is the probability of success for Project B?
A 0.3
B 0.2
C 0.35
D 0.15
E 0.12
第10题
200 Using the figure in the Special Window, what is the probability of success for Project B?
A. 0.30
B. 0.20
C. 0.35
D.0.15
E.0.12
为了保护您的账号安全,请在“上学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!