第2题
A.建筑结构地震影响系数应根据烈度、场地类别、设计地震分组、结构自震周期以及阻尼比确定
B.地震影响系数曲线为分段曲线,各曲线段有各自不同的曲线方程
C.当阻尼比不等于0.05时,曲线下降段衰减指数、直线下降段斜率调整系数均需进行修正
D.直线下降段的下降斜率调调整系数应大于等于1.0
第3题
The cyclically adjusted budget deficit is the budget deficit corrected for the effects of the business cycle. In other words, it is the budget deficit that the government would be running if unemployment were at the natural rate. (It is also called the full-employment budget deficit.) Some economists have proposed the rule that the cyclically adjusted budget deficit always be balanced. Compare this proposal to a strict balanced-budget rule. Which is preferable? What problems do you see with the rule requiring a balanced cyclically adjusted budget?
第4题
A.即使合同中没有约定价格调整条款,但从公平角度出发,发包人也必须对承包人应价格变动导致的成本增加予以补偿
B.建设工程一般周期较长,容易遭受各种风险影响,可能给承包人造成较大损失。如合同中约定了价格调整条款,可以比较公正地解决这一承包人无法控制的风险损失
C.无论是单价合同还是总价合同,都可以约定价格调整条款
D.合同计价方式及价格调整方式共同确定了工程承包合同的实际价格,直接影响着承包人的经济利益
第5题
A.减少储蓄配置,减少债券配置,增加股票配置,增加股票型基金配置,增加房产配置
B.减少储蓄配置,减少债券配置,增加股票配置,减少股票型基金配置,减少房产配置
C.减少储蓄配置,增加债券配置,增加股票配置,增加股票型基金配置,减少房产配置
D.减少储蓄配置,增加债券配置,增加股票配置,减少股票型基金配置,增加房产配置
第6题
第7题
A.性价比法一般适用于具有通用技术、性能标准,没有特殊性、单一性要求,但价格过低会影响合同履行或工程质量的招标项目
B.采用全寿命周期成本计算法仅考虑工程或货物的各项财务成本,而不考虑技术、品牌、人员、资质、业绩等因素
C.政府采购项目的最低评标价法对超出招标要求的商务、技术和服务等响应要素不进行量化折价,所以这种评标方法应归属于经评审的最低投标价法
D.栅栏评标法既不对融资方案、技术和管理方案、项目协议响应方案等技术因素进行价格折算,也不对商务因素进行价格调整
第8题
A.正确
B.错误