第1题
How much time does the typical project manager spend communicating (formal and informal)?
A 40% - 60%
B 30% - 70%
C 60% - 80%
D 75% - 90%
E 25% - 55 %
第2题
An informal communication network on a project and within an organization is called a(n):
A free upward flow
B free horizontal flow
C unrestricted communication flow
D grapevine
E open network
第3题
107 How much time does the typical project manager spend communicating (formal and informal)? A. 40% - 60%
B. 30% - 70%
C. 60% - 80%
D. 75% - 90%
E. 25% - 55 %
第4题
A.Individual behavior be changed immediately and prepare to the next conference.
B.Write a meeting about culture and conference rules memo.
C.Discuss good preparation at the bebinning of the next meetin
D.Convene fewer but more substertial meetings.
第5题
189 How much time does the typical project manager spend communicating (formal and informal)? A. 40% - 60%
B. 30% - 70%
C. 60% - 80%
D. 75% - 90%
E. 25% - 55 %
第6题
4 An informal communication network on a project and within an organization is called a(n):
A. free upward flow
B. free horizontal flow
C. unrestricted communication flow
D. grapevine
E. open network
第7题
156 An informal communication network on a project and within an organization is called a(n):
A. free upward flow
B. free horizontal flow
C. unrestricted communication flow
D. grapevine
E. open network
第8题
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第9题
5 The scope baseline/project charter is prepared by the:
A. Project manager
B. Project manager and project office
C. Project manager, project office and functional team
D. Project manager, project office, functional team and project sponsor
E. Project manager, project sponsor and customer/user
第10题
The scope baseline/project charter is prepared by the:
AProject manager
BProject manager and project office
CProject manager, project office and functional team
DProject manager, project office, functional team and project sponsor
EProject manager, project sponsor and customer/user
为了保护您的账号安全,请在“上学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!