The project scope/charter baseline includes:
A.Summary of background conditions defining the project.
B.Organization, authority and responsibility relationships.
C.Functions to be performed.
D.Resource requirement schedule including time estimates.
E.All of the above.
第2题
41 The project scope/charter baseline includes:
A. Summary of background conditions defining the project.
B. Organization, authority and responsibility relationships.
C. Functions to be performed.
D. Resource requirement schedule including time estimates.
E. All of the above
第3题
● The project scope/charter baseline includes:
A Summary of background conditions defining the project.
B Organization, authority and responsibility relationships.
C Functions to be performed.
D Resource requirement schedule including time estimates.
E All of the above.
第4题
The scope baseline/project charter is prepared by the:
AProject manager
BProject manager and project office
CProject manager, project office and functional team
DProject manager, project office, functional team and project sponsor
EProject manager, project sponsor and customer/user
第5题
5 The scope baseline/project charter is prepared by the:
A. Project manager
B. Project manager and project office
C. Project manager, project office and functional team
D. Project manager, project office, functional team and project sponsor
E. Project manager, project sponsor and customer/user
第6题
123 The scope baseline/project charter is prepared by the:
A. Project manager
B. Project manager and project office
C. Project manager, project office and functional team
D. Project manager, project office, functional team and project sponsor
E. Project manager, project sponsor and customer/user
第7题
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第8题
(75)
A. Project Scope Statement
B. Project Management Plan
C. Forecasts
D. Project Charter
第9题
145 The initial document that formally recognizes the existence of a project is the _____ .
A. Scope baseline
B. Management plan
C. Project charter
D. Configuration control report
E. None of the above
第10题
27 The initial document that formally recognizes the existence of a project is the _____ .
A. Scope baseline
B. Management plan
C. Project charter
D. Configuration control report
E. None of the above