196 Giving a part of project work to a contractor is an example of:
A. risk mitigation
B. risk assignment
C. risk delegation
D. risk deflection
E. risk assumption
第2题
78 Giving a part of project work to a contractor is an example of:
A. risk mitigation
B. risk assignment
C. risk delegation
D. risk deflection
E. risk assumption
第3题
The contractual statement of work (CSOW)
A.Must be the same as the proposal statement of work
B.Does not identify reporting requirements
C.Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D.Identifies the contractor's organizational structure for the project
E.All of the above
第4题
A.Shift more of the work to later in the schedule to allow time for the customer to get the funds .
B.Reduce the scope of work and enter closure .
C.Stop work .
D.Release part of the project team .
第5题
A.Cost plus fixed fee
B.Fixed price
C.Fixed price plus incentive fee
D.B and C
第6题
● The contractual statement of work (CSOW)
A Must be the same as the proposal statement of work
B Does not identify reporting requirements
C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D Identifies the contractor's organizational structure for the project
E All of the above
第7题
A.incomplete because the buyer is not pleased
B.incomplete because the specs are incorrect
C.compete because the contractor meets the terms and conditions of the contract
D.complete because the contractor is satisfied
第8题
86 The contractual statement of work (CSOW)
A. Must be the same as the proposal statement of work
B. Does not identify reporting requirements
C. Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D. Identifies the contractor's organizational structure for the project
E. All of the above
第9题
168 The contractual statement of work (CSOW)
A. Must be the same as the proposal statement of work
B. Does not identify reporting requirements
C. Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D. Identifies the contractor's organizational structure for the project
E. All of the above