请帮忙给出正确答案和分析,谢谢!
第1题
167 The purpose of project Risk Management is to:
A. Identify those factors that will adversely impact project objectives.
B. Assess the impact of adverse project factors.
C. Assess the probability of adverse project factors.
D. A and C
E. All of the above
第2题
85 The purpose of project Risk Management is to:
A. Identify those factors that will adversely impact project objectives.
B. Assess the impact of adverse project factors.
C. Assess the probability of adverse project factors.
D. A and C
E. All of the above
第3题
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第4题
● Risk management allows the project manager and the project team not to(71).
(71)
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第5题
In Project Risk Management, Risk Response may include actions to:
A reduce the probability of risk events
B change the scope, budget, schedule or quality specifications of the project
C reduce the consequences or severity of impacts of a potential risk event
D A and C
E All of the above.
第6题
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第7题
Risk management allows the project manager and the project team not to (71).
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第8题
Risk management allows the project manager and the project team not to (71).
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第9题
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第10题
In Project Risk Management, Risk Response may include actions to:
A. reduce the probability of risk events
B. change the scope, budget, schedule or quality specifications of the project
C. reduce the consequences or severity of impacts of a potential risk event
D. A and C
E. All of the above