第1题
172 Smoothing out resource requirements from period to period is called resource _____.
A. Allocation.
B. Partitioning
C. Leveling.
D. Quantification
E. None of above
第2题
54 Smoothing out resource requirements from period to period is called resource _____.
A. Allocation.
B. Partitioning
C. Leveling.
D. Quantification
E. None of above
第3题
Resource leveling _____.
A.Allocates resources to activities to find shortest schedule within fixed resource limits.
B.Smoothes out resource requirements by rescheduling activities within their float time.
C.Smooths out resource requirements by substituting activities with unassigned resources.
D.Attempts to reduce resource requirements within a constraint on project duration
E.B or D
第4题
● Resource leveling _____.
A Allocates resources to activities to find shortest schedule within fixed resource limits.
B Smoothes out resource requirements by rescheduling activities within their float time.
C Smooths out resource requirements by substituting activities with unassigned resources.
D Attempts to reduce resource requirements within a constraint on project duration
E B or D
第5题
171 Resource leveling _____.
A. Allocates resources to activities to find shortest schedule within fixed resource limits.
B. Smoothes out resource requirements by rescheduling activities within their float time.
C. Smooths out resource requirements by substituting activities with unassigned resources.
D. Attempts to reduce resource requirements within a constraint on project duration
E. B or D
第6题
53 Resource leveling _____.
A. Allocates resources to activities to find shortest schedule within fixed resource limits.
B. Smoothes out resource requirements by rescheduling activities within their float time.
C. Smooths out resource requirements by substituting activities with unassigned resources.
D. Attempts to reduce resource requirements within a constraint on project duration
E. B or D
第7题
● Sources for data on activity durations and resource requirements can be gathered from which of the following:
A Past project records (historical data)
B Commercial techniques (standard practices, rules of thumb)
C Past project team members knowledge (experience, oldtimers)
D All of the above
E A and C only
第8题
33 Sources for data on activity durations and resource requirements can be gathered from which of the following:
A. Past project records (historical data)
B. Commercial techniques (standard practices, rules of thumb)
C. Past project team members knowledge (experience, oldtimers)
D. All of the above
E. A and C only
第9题
151 Sources for data on activity durations and resource requirements can be gathered from which of the following:
A. Past project records (historical data)
B. Commercial techniques (standard practices, rules of thumb)
C. Past project team members knowledge (experience, oldtimers)
D. All of the above
E. A and C only
第10题
A.DRP (Distribution Resource Planning)
B.LRP (Logistics Resource Planning)
C.MRP (Material Requirements Planning)
D.ERP (Enterprise Resource Planning)