The most crucial time for project risk assessment is (75) .
A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
第2题
A be completed in reduced overall time than other projects.
B be in a higher risk category than other projects.
C not be compatible with project risk and assessment
D A and B
E All of the above.
第3题
60 "Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .
A. be completed in reduced overall time than other projects.
B. be in a higher risk category than other projects.
C. not be compatible with project risk and assessment
D. A and B
E. All of the above
第4题
It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
第5题
178 "Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .
A. be completed in reduced overall time than other projects.
B. be in a higher risk category than other projects.
C. not be compatible with project risk and assessment
D. A and B
E. All of the above
第6题
193 It is useful to conduct project risk assessment according to the project's
A. charter
B. statement of work
C. Work Breakdown structure
D. network
E. budget
第7题
111 It is useful to conduct project risk assessment according to the project's
A. charter
B. statement of work
C. Work Breakdown structure
D. network
E. budget
第8题
Which of the following actions is an example of risk response:
A adjust project parameters (scope, time, quality ...)
B reduce the probability of potential project risk events
C reduce the consequences of potential project risk events
D wait until a problem actually happens, then deal with it in the most effective and efficient manner.
E A, B and C only
第9题
23 Which of the following actions is an example of risk response:
A. adjust project parameters (scope, time, quality ...)
B. reduce the probability of potential project risk events C. reduce the consequences of potential project risk events
D. wait until a problem actually happens, then deal with it in the most effective and efficient manner.
E. A, B and C only