Schedule control is concerned with all the following except (74)
A.influencing the factors that create schedule changes to ensure that the changes are beneficial
B.determing that the schedule has changed
C.managing the actual changes when and as they occur
D.changing the shedule based on customer demands
第2题
The intention of the__(75)__is to schedule,organize and control all activities to achieve the project goal eventually.No matter how difficult it is and what kind of risks are ther
A.
B.project work breakdown
C.project security authentication
D.project management
E.project flowchart
第3题
A、Inside
B、Outside
C、All of the above
D、None of the above
第4题
The Work Breakdown Structure (WBS) is the basis for communicating:
A.Project scope, cost control, schedule, quality
B.Project objectives, dependencies, plan, cost control
C.Project scope, schedule, staffing, cost control
D.Project scope, quality, schedule, dependencies
E.Project budget, schedule, risk factors, work assignments.
第5题
A.the quality of the schedule and cost control analysis
B.customer satisfaction
C.customer compromise in defining its needs
D.exceeding customer requirements through gold-plating
第6题
● Configuration (baseline) control monitors performance against the
A scope baseline
B original schedule
C original budget
D All of the above.
E None of the above.
第7题
65 Configuration (baseline) control monitors performance against the
A. scope baseline
B. original schedule
C. original budget
D. All of the above.
E. None of the above
第8题
183 Configuration (baseline) control monitors performance against the
A. scope baseline
B. original schedule
C. original budget
D. All of the above.
E. None of the above
第9题
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第10题
A Work breakdown structure
B milestone review and schedule technique
C cost/schedule control system
D planning programming budget system
E program and evaluation review technique