第1题

Estimating schedule activity costs involves developing an (74) of the cost of the resource

Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.

A.accuracy

B.approximation

C.specification

D.summary

点击查看答案

第2题

Estimating schedule activity costs involves developing an (74) of the cost of the resource
s needed to complete each schedule activity.

A.accuracy

B.approximation

C.specification

D.summary

点击查看答案

第3题

Estimating schedule activity costs involves developing an(69)of the costs of the resources

Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.

A.accuracy

B.approximation

C.specification

D.summary

点击查看答案

第4题

Estimating schedule activity costs involves develo...

Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.

空白(1)处填()

A. accuracy

B. approximation

C. specification

D. summary

点击查看答案

第5题

● Project schedule management is made up of six management processes including: activity d
efinition, activity sequencing, (71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating

点击查看答案

第6题

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

A.activity duration estimating, schedule developing, activity resource estimating

B.activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating

点击查看答案

第7题

● Project schedule management is made up of six management processes including: activity d
efinition, activity sequencing, (71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating

点击查看答案

第8题

Parametric cost estimating involvesA.using the WBS to do bottom up estimatesB.defining the

Parametric cost estimating involves

A.using the WBS to do bottom up estimates

B.defining the perimeters of the life-cycle

C.calculating the individual estimates of work packages

D.using a statistical model to estimate costs

E.A and C

点击查看答案

第9题

101Parametric cost estimating involves A.using the WBS to do bottom up estimates B.definin

101 Parametric cost estimating involves

A. using the WBS to do bottom up estimates

B. defining the perimeters of the life-cycle

C. calculating the individual estimates of work packages

D. using a statistical model to estimate costs

E. A and C

点击查看答案

第10题

19Parametric cost estimating involves A.using the WBS to do bottom up estimates B.defining

19 Parametric cost estimating involves

A. using the WBS to do bottom up estimates

B. defining the perimeters of the life-cycle

C. calculating the individual estimates of work packages

D. using a statistical model to estimate costs

E. A and C

点击查看答案
下载上学吧APP
客服
TOP
重置密码
账号:
旧密码:
新密码:
确认密码:
确认修改
购买搜题卡查看答案
购买前请仔细阅读《购买须知》
请选择支付方式
微信支付
支付宝支付
选择优惠券
优惠券
请选择
点击支付即表示你同意并接受《服务协议》《购买须知》
立即支付
搜题卡使用说明

1. 搜题次数扣减规则:

功能 扣减规则
基础费
(查看答案)
加收费
(AI功能)
文字搜题、查看答案 1/每题 0/每次
语音搜题、查看答案 1/每题 2/每次
单题拍照识别、查看答案 1/每题 2/每次
整页拍照识别、查看答案 1/每题 5/每次

备注:网站、APP、小程序均支持文字搜题、查看答案;语音搜题、单题拍照识别、整页拍照识别仅APP、小程序支持。

2. 使用语音搜索、拍照搜索等AI功能需安装APP(或打开微信小程序)。

3. 搜题卡过期将作废,不支持退款,请在有效期内使用完毕。

请使用微信扫码支付(元)
订单号:
遇到问题请联系在线客服
请不要关闭本页面,支付完成后请点击【支付完成】按钮
遇到问题请联系在线客服
恭喜您,购买搜题卡成功 系统为您生成的账号密码如下:
重要提示: 请勿将账号共享给其他人使用,违者账号将被封禁。
发送账号到微信 保存账号查看答案
怕账号密码记不住?建议关注微信公众号绑定微信,开通微信扫码登录功能
警告:系统检测到您的账号存在安全风险

为了保护您的账号安全,请在“上学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!

- 微信扫码关注上学吧 -
警告:系统检测到您的账号存在安全风险
抱歉,您的账号因涉嫌违反上学吧购买须知被冻结。您可在“上学吧”微信公众号中的“官网服务”-“账号解封申请”申请解封,或联系客服
- 微信扫码关注上学吧 -
请用微信扫码测试
选择优惠券
确认选择
谢谢您的反馈

您认为本题答案有误,我们将认真、仔细核查,如果您知道正确答案,欢迎您来纠错

上学吧找答案